the ground and wall. Each additional truss is lifted into position, generally 600 mm (24 in.) on centre, toe-nailed to the top plates and temporarily braced (Figure 80). When all trusses are plumbed and properly positioned, they are braced permanently (Figure 81); a) permanent 80 Temporary bracing of roof trusses Note: Gable ends are normally sheathed prior to installation of end braces. 81 Permanent bracing of roof trusses A Plan View lateral brace top chord ridge line diagonal brace nailed to web—repeat at approximate 6 m (20 ft.) intervals as required by truss manufacturer lateral bracing B End Elevation 38 x 89 mm (2 x 4 in.) web bracing as required by truss manufacturer C Side Elevation sheathing blocking lateral brace diagonal forms braced bay—repeat at both ends and at approximate 6 m (20 ft.) intervals as required by truss manufacturer ceiling